Capital Program Dashboard

Capital Program Dashboard

As of 6/30/2017
Project Locations (All Programs)
* Projects classified as Systemwide are not reflected on the map.

To see a project name, zoom in and hover over a locator on the map above. For details on the project click the link.

Project Locations (VTA Transit)
* Projects classified as Systemwide are not reflected on the map.

To see a project name, zoom in and hover over a locator on the map above. For details on the project click the link.

Current Appropriation by Category (VTA Transit)
Projects By Phase (VTA Transit)
Current Appropriation by Project Type (VTA Transit)

Project Details (VTA Transit) Data Download Report Glossary
Budget Schedule
Project Name Photos Phase Original Cost Estimate Current Cost Estimate Original Estimate vs. Current Current Appropriation Scope Change Original Start Current Start Original Completion Current Completion
Revenue Vehicles & Equipment
Paratransit Vehicles and Equipment Planning $3,475,650 $3,475,650 0% $3,475,650 Jun-12 Jun-12 Dec-15 Jun-17
40' Bus Procurement Procurement $172,000,000 $46,341,743 -73% $46,341,743 Jun-13 Jun-13 Jun-17 Jun-17
60' Articulated Bus Procurement Design $52,214,000 $52,068,315 0% $52,068,315 Jun-13 Jun-13 Jun-15 Jun-19
40' Bus Procurement FY16 Design $60,875,229 $57,426,951 -6% $60,875,229 Jun-15 Jun-15 Jun-19 Jun-19
Wheelchair Ramp Replacement on 70 Buses Design $1,050,000 $1,050,000 0% $1,050,000 Jun-15 Jun-15 Feb-16 Jun-17
Light Rail Vehicle CCTV Upgrade Planning $5,500,000 $8,500,000 55% $8,715,000 Dec-16 Dec-16 Dec-17 Aug-18
3-Position Exterior Bike Racks for Buses Design $900,000 $900,000 0% $900,000 Jul-15 Jun-15 Jun-16 Jun-17
Electric Bus Pilot Project Planning $4,000,000 $15,500,000 288% $15,500,000 Jul-15 Jun-15 Aug-17 Sep-17
Tire Barrier Retrofit Planning $625,000 $625,000 0% $625,000 Aug-15 Jun-15 May-16 Jun-17
Paratransit Fleet Program Completed $2,323,000 $2,323,000 0% $2,323,000 Sep-16 Sep-16 Jun-17 Oct-17
Passenger Facilities
High Volume Bus Stop Improvement Design $2,750,000 $1,900,000 -31% $1,900,000 Jul-12 Aug-12 Jul-13 Oct-18
Ped Swing Gates Replacement Planning $370,000 $4,850,000 1211% $1,450,000 increase icon Jun-12 Sep-12 Nov-13 Dec-19
Bus Stop Pavement/Duckout Improv. FY14 Construction $1,044,500 $1,019,878 -2% $1,131,878 Jun-13 Jun-13 May-15 Jun-18
Infrastructure-Add'l ClipperFare Devices Close-out $550,000 $550,000 0% $475,000 Jun-13 Jun-13 Jun-15 Dec-17
RTI Signs at Light Rail Stations Ongoing $869,500 $2,089,500 140% $2,339,500 Feb-15 Feb-15 Dec-16 Aug-17
LR Facilities LED Lighting Retrofit Planning $937,500 $937,500 0% $937,500 Jun-15 Jun-15 Jun-16 Dec-20
Ticket Vending Machines - Stadium Events Design $660,000 $660,000 0% $1,317,739 Jun-15 Jun-15 Jan-16 Jun-18
Light Rail Station Signage Replacement Design $2,000,000 $2,000,000 0% $2,000,000 Jun-15 Feb-16 Aug-17 Dec-19
Transit Center Park & Ride Upgrades FY16 Close-out $500,000 $609,460 22% $609,460 Jun-15 Jun-15 Jun-17 Dec-17
Vasona Corridor Pedestrian Back Gates Planning $1,300,000 $1,300,000 0% $1,300,000 Jun-15 Jun-15 Jun-17 Sep-20
Diridon Sta. Intermodal Conceptual Plan Planning $1,000,000 $6,000,000 500% $1,000,000 Dec-16 Jan-16 Dec-17 Jun-19
Operating Facilities & Equipment
HazMat/Fac. Design and Construction Close-out $466,671 $264,344 -43% $264,344 decrease icon Sep-05 Nov-02 Oct-06 Dec-17
Bus Signal Priority Construction $929,719 $911,042 -2% $911,042 Jun-06 Jun-07 Nov-07 Dec-17
Green Facility Improvements Construction $5,200,000 $6,200,000 19% $6,200,000 Jun-07 Jun-07 Jun-15 Dec-17
Pavement Management Program-FY09 Design $716,928 $716,928 0% $716,928 increase icon Jun-08 Jun-08 Jun-09 Mar-19
SCADA System Hardening Construction $3,802,491 $3,902,202 3% $4,233,554 increase icon Mar-11 Mar-11 Mar-13 Sep-17
GFCI (switchgear) Testing & Replacement Procurement $212,175 $312,175 47% $312,175 increase icon Jun-11 Apr-11 Jun-13 Sep-18
LRV Body Shop-Dust Separation Wall Construction $545,000 $1,045,000 92% $1,045,000 increase icon Jun-13 Oct-11 Jun-14 Mar-18
LRV Maintenance Shop Hoist Construction $3,437,320 $5,051,370 47% $5,051,370 increase icon Jun-13 Oct-12 Jun-14 Mar-18
River Oaks Auditorium & Lobby Reconfig Close-out $500,000 $555,000 11% $555,000 increase icon Jun-12 Jun-12 Jun-13 Jun-17
Radio System Installation FY13 Construction $1,300,000 $504,285 -61% $504,285 Jun-12 Jun-12 Mar-14 Oct-17
Downtown Customer Service Ctr.Move(2013) Close-out $576,950 $967,117 68% $967,117 increase icon Jan-13 Feb-13 Jul-13 Jun-17
Replace Wheel Turning Machine Planning $2,600,000 $5,809,500 123% $2,600,000 Jun-13 Jun-13 Jun-15 Dec-20
LED Exterior Lighting Replacement Design $900,000 $900,000 0% $900,000 Dec-14 Jun-13 Dec-15 Dec-17
Cerone Propane Tank Replacement Planning $350,000 $1,110,000 217% $1,110,000 Jun-14 Jun-13 Jun-15 Sep-19
Facilities Maint. Equipment Program FY14 Design $1,125,900 $979,900 -13% $979,900 Jun-13 Jun-13 Jun-15 Dec-17
Paving Management Program FY14 Construction $2,316,000 $2,316,000 0% $2,316,000 Jun-13 Jun-13 Jun-15 Jun-17
Cerone Boiler Replacement Planning $300,000 $1,166,000 289% $1,166,000 Jun-13 Jun-13 Aug-14 Jun-19
Cerone Emergency Generator Replacement Planning $1,200,000 $2,460,000 105% $1,200,000 Jun-14 Jun-13 Jun-15 Jun-19
CCTV Surveillance Equipment Close-out $2,144,129 $3,086,403 44% $3,086,403 increase icon Apr-14 Apr-14 Mar-16 Mar-18
CCTV Equipment Construction $1,500,000 $3,701,025 147% $3,701,025 Sep-14 Sep-14 Mar-17 Sep-18
OCC Rail control Reconfiguration Completed $100,000 $150,000 50% $150,000 increase icon May-15 May-15 Dec-16 Aug-17
Guadalupe SCADA & OCC UPS Replacement Procurement $105,413 $105,413 0% $105,413 Mar-15 Apr-15 Mar-16 Dec-17
Automated Wheel Measurement Sys LR Veh. Planning $878,750 $878,750 0% $878,750 Aug-15 Jun-15 Jun-18 Jun-18
Guadalupe Train Wash Replacement Planning $1,810,000 $1,810,000 0% $1,810,000 Jun-15 Jun-15 Jun-17 Dec-20
Facilities Maint. Equipment Program FY16 Planning $949,212 $949,212 0% $949,212 Jun-15 Jun-15 Jun-17 Dec-19
HVAC Replacement Program FY16 Planning $1,300,000 $1,306,495 0% $1,306,495 Jun-15 Jun-15 Jun-17 Jun-18
Pavement Management Program FY16 Design $910,000 $910,000 0% $910,000 Jun-15 Jun-15 Jun-17 Dec-17
Painting Management Program FY16 Planning $1,540,000 $1,540,000 0% $1,540,000 Jun-15 Jun-15 Jun-17 Jun-18
Roofing Management Program FY16 Planning $923,000 $923,000 0% $923,000 Jun-15 Jun-15 Jun-17 Jun-18
Chaboya Yard Well Removal Planning $245,000 $245,000 0% $245,000 Jun-15 Jun-15 Jun-16 Jun-19
Employee Facility Updates at Chaboya Planning $533,000 $533,000 0% $533,000 Jun-15 Jun-15 Jun-17 Jun-18
Enhanced CCTV Sys-Major Events Hardening Close-out $1,897,488 $1,897,488 0% $1,897,488 Sep-15 Oct-15 Feb-16 Jun-19
SCADA and TVM Network Separation Planning $5,114,682 $1,150,000 -78% $1,150,000 Aug-16 Aug-16 Dec-20 Feb-20
Eastridge Paratransit Facility Construction $2,800,000 $5,799,155 107% $5,799,155 Oct-16 Oct-16 Jun-17 Dec-17
Emergency Electrical Repair River Oaks Design $224,175 $225,000 0% $225,000 Jun-16 Nov-16 Dec-16 Dec-17
Non-Revenue Vehicles
NRV Procurement Project Procurement $1,931,430 $1,931,430 0% $1,931,430 Jun-11 Jun-11 Jun-13 Jun-17
Non-Revenue Vehicle Procurement FY14 Procurement $1,071,600 $1,071,600 0% $1,071,600 Jun-13 Jun-13 Jun-15 Sep-17
Non-Revenue Vehicle Procurement FY16 Procurement $863,200 $863,200 0% $863,200 Jun-15 Sep-15 Jun-17 Mar-18
Miscellaneous
VETS Transpt.& Community Living Initiat. Design $2,050,000 $2,050,000 0% $2,050,000 Jul-12 Jun-13 Dec-14 Jun-17
Core Connectivity Study Planning $320,000 $320,000 0% $320,000 Feb-15 Feb-15 Jun-17 Nov-17
Slow Speed Zone Study Planning $300,000 $600,000 100% $600,000 Mar-15 May-15 Dec-17 Dec-19
North Bayshore Transportation Study Planning $250,000 $250,000 0% $250,000 Jan-16 Feb-16 Sep-16 Dec-17
Light Rail Way, Power & Signal
Rail Replacement & Rehab Construction $20,673,908 $20,673,924 0% $20,673,924 increase icon Jun-09 Feb-09 Jun-20 Dec-19
Traction Power Substation Procurement Design $17,379,385 $20,259,715 17% $20,259,715 increase icon Jun-10 Sep-09 Jun-19 Jun-19
Guada.OCS Rehab & Replacement Program Design $29,103,546 $9,075,576 -69% $9,075,576 decrease icon Jun-10 Jun-09 Jun-20 Dec-20
LRT Crossovers and Switches Construction $3,448,773 $3,943,492 14% $3,943,492 increase icon Jun-14 Jun-11 Jun-17 Dec-19
Bridge Repair/Hamilton Struct.Stabilizat Planning $1,700,000 $3,200,000 88% $2,800,000 increase icon Jun-11 Mar-12 Dec-14 Jun-19
Guada Signal Assessment/SCADA Sys Replac Design $20,000,000 $3,500,000 -82% $3,500,000 decrease icon Jun-12 Jun-12 Jun-17 Dec-17
N 1st & DT SJ LR Speed Improvmt Design Design $3,832,000 $1,537,000 -60% $1,537,000 Dec-11 Apr-12 Oct-12 Dec-17
Update Santa Teresa Interlock Sig. House Construction $860,000 $2,160,000 151% $2,160,000 increase icon Jun-11 Jun-12 Jun-14 Sep-18
LR Transit Signal Priority Improvements Procurement $1,792,813 $2,132,813 19% $2,132,813 Aug-12 Aug-12 Sep-13 Oct-19
Upgrade Ohlone/Chynoweth Interlocking Planning $1,200,000 $1,200,000 0% $1,200,000 Jun-13 Jun-13 Dec-16 Dec-20
Track Intrusion Abatement FY14 Design $2,000,000 $2,000,000 0% $2,000,000 Jun-13 Jun-13 May-15 Jun-19
SCADA Rehabilitation Construction $2,040,763 $1,803,451 -12% $1,803,451 Jun-15 Jun-15 Jun-16 Sep-17
Downtown San Jose Speed Improvement-Ph1 Design $6,000,000 $5,900,000 -2% $5,900,000 Dec-16 Jun-16 Dec-17 Jun-18
Light Rail Crossovers and Switches FY16 Planning $8,200,000 $4,100,000 -50% $4,100,000 Jun-16 Jun-15 May-19 Jun-20
Rail Rehabilitation & Replacement FY16 Planning $4,500,000 $4,500,000 0% $4,500,000 Jun-16 Jun-16 Mar-19 Sep-20
Traction Power Substa Procurement FY16 Planning $9,000,000 $9,000,000 0% $9,000,000 Jun-16 Jun-16 Dec-18 Dec-21
Bridge and Structure Repairs FY16 Planning $1,500,000 $700,000 -53% $700,000 Jun-15 Nov-15 Jun-17 Dec-20
Track Intrusion Abatement FY16 Design $2,000,000 $2,000,000 0% $2,000,000 Jun-16 Jun-15 Jun-18 Dec-20
Traction/Substation Power Monitoring Sys Planning $234,542 $234,542 0% $234,542 Jun-15 Jun-15 Jun-16 Dec-17
Information Sys & Technology
SCADA GEisys Software Upgrade Planning $1,250,000 $1,250,000 0% $1,250,000 Jun-11 Jun-11 Jun-12 Jun-18
Trapeze OPS Software Installation Construction $3,200,000 $3,200,000 0% $3,200,000 Sep-11 Oct-11 Sep-13 Jun-18
VTA Gigabit Network Project Construction $1,425,000 $1,425,000 0% $919,617 Jun-11 Jun-11 Mar-13 Aug-17
Record Management Program Construction $2,788,000 $2,788,000 0% $2,788,000 Dec-11 Jul-12 Dec-16 Feb-18
Train to Wayside Communicat. Sys Upgrade Procurement $250,000 $1,605,750 542% $1,605,750 Jun-13 Jun-13 Dec-16 May-20
TERM Lite Deployment Construction $600,000 $400,000 -33% $400,000 Dec-14 Dec-14 Dec-15 Dec-17
SAP Plant Maint. & Materials Management Design $300,000 $300,000 0% $300,000 Dec-14 Jun-13 Dec-15 Dec-19
Bus. Process Automation - Acts. Payable Construction $455,000 $732,000 61% $732,000 Aug-14 Oct-14 Mar-15 Feb-18
Upgrade Countywide Travel Demand Model Planning $650,000 $650,000 0% $650,000 Jun-13 Jun-13 Jun-15 Dec-17
Telecommunications System Updates Construction $375,000 $375,000 0% $375,000 Jun-13 Jun-13 Jun-15 Oct-17
CAD-AVL Update Design $7,000,000 $28,707,975 310% $28,707,975 Jun-13 Jun-13 Jun-15 Dec-20
Upgrade LR Ring #1 Communications Equip. Planning $2,200,000 $2,200,000 0% $2,200,000 Oct-14 Jun-13 Oct-15 Dec-19
Radio System Upgrade Procurement $2,500,000 $4,850,000 94% $5,550,000 Jun-13 Jun-13 Jun-15 Nov-17
Business Process Automation - Payroll Construction $295,000 $663,000 125% $663,000 Feb-14 Feb-14 Dec-15 Aug-17
Mobile Network-Full Fleet Wi-Fi Construction $650,000 $650,000 0% $650,000 Jun-14 Sep-14 Sep-15 Jun-17
CCTV Emergency Storage Expansion Construction $175,000 $175,000 0% $175,000 Oct-14 Oct-14 Jan-15 Jun-17
Interactive Customer Message Boards Construction $690,000 $690,000 0% $690,000 Nov-14 Nov-14 Jun-17 Jan-18
Multimodal TripDataCollector/Planner APP Design $125,000 $275,000 120% $275,000 increase icon Jan-15 Jan-15 Jun-15 Jun-18
Demand Response & Subscription Solution Ongoing $400,000 $400,000 0% $400,000 Jan-15 Jan-15 Sep-15 Dec-17
Network and Gigabit Fiber Upgrade Construction $700,000 $700,000 0% $700,000 Jun-15 Jun-15 Jun-16 Nov-17
Server Refresh Procurement $500,000 $500,000 0% $800,000 Jun-15 Jun-15 Jun-16 Jun-17
CreditCard Authorization Sys Enhancement Planning $180,000 $180,000 0% $180,000 Jun-15 Jun-15 Jun-17 Sep-17
GIS Program Development Construction $250,000 $250,000 0% $250,000 Jun-15 Jun-15 Jun-17 Jun-18
Server Security Repl/Performance Upgrade Design $1,050,000 $1,050,000 0% $1,675,000 Jun-15 Jun-15 Jun-16 Jul-17
Electr.Procure./Contract Bidding Process Planning $210,000 $210,000 0% $210,000 Dec-16 Jun-16 Jul-17 Feb-18
Connected Vehicles Technology Platform Planning $1,000,000 $1,000,000 0% $1,000,000 Jun-15 Jun-15 Dec-16 Dec-17
Dynamic Transit Pilot Service Planning $2,000,000 $2,000,000 0% $2,000,000 Jun-15 Jun-15 Jun-17 Jun-18
Project/Construction Management Software Design $325,000 $325,000 0% $325,000 Jan-16 Dec-16 Dec-16 Jun-22
B-106 Technology Build Out Completed $127,850 $360,165 182% $360,165 increase icon Mar-16 Mar-16 Aug-16 Jun-17
Trapeze Paratransit Scheduling Software Construction $1,349,000 $1,349,000 0% $1,349,000 Sep-16 Sep-16 Jun-17 Dec-17
Advanced Cyber Security Planning $600,000 $200,000 -67% $800,000 Feb-17 Feb-17 Jul-17 Sep-17
Project Locations (2000 Measure A)
* Projects classified as Systemwide are not reflected on the map.

To see a project name, zoom in and hover over a locator on the map above. For details on the project click the link.

Current Appropriation by Category (2000 Measure A)
Projects By Phase (2000 Measure A)
Current Appropriation by Project Type (2000 Measure A)

Project Details (2000 Measure A) Data Download Report Glossary
Budget Schedule
Project Name Photos Phase Original Cost Estimate Current Cost Estimate Original Estimate vs. Current Current Appropriation Scope Change Original Start Current Start Original Completion Current Completion
SVRT Program
Berryessa Extension Project - SVBX Construction $2,421,273,000 $2,421,272,972 0% $2,157,061,767 Dec-10 Jan-10 Jun-18 Jun-23
20 Non New Starts BART Vehicles Construction $82,500,000 $67,806,989 -18% $67,806,989 Dec-11 Mar-12 Dec-16 May-23
BART HMC and ROW (excl. HYPSC) Construction $136,100,000 $150,760,397 11% $150,760,397 Dec-11 Dec-11 Jun-18 Jun-21
Montague Reconstruction Project Construction $17,051,000 $21,969,513 29% $21,969,513 increase icon Mar-13 May-13 Jun-18 Mar-20
BART Core System Modifications Design $46,000,000 $46,000,000 0% $32,017,927 Jun-13 Jun-13 Jun-18 Dec-23
Upper Penitencia Creek Trail Connector Construction $2,415,100 $2,476,569 3% $2,476,569 Oct-13 Oct-13 Dec-16 Jun-20
Montague Exwy POC Design Design $844,000 $2,301,150 173% $2,301,150 Sep-15 Sep-15 Jun-17 Dec-21
FRR-Lower Berryessa Creek - VTA Close-out $5,600,000 $4,821,300 -14% $4,821,300 Jun-08 Jan-07 Dec-11 Dec-19
MWT Project Close-out $137,895,519 $142,962,444 4% $145,440,588 May-09 Dec-05 Dec-14 Dec-21
LBC Project (C210) Close-out $34,128,000 $33,985,108 0% $33,985,108 Oct-08 Jan-07 Dec-11 Dec-19
SVRT Project Development After FY09 Planning $4,700,000,000 $4,700,000,000 0% $136,293,159 May-09 Jun-09 Dec-26 Jun-27
Passenger Facilities
Berryessa Garage Solar Panel System Completed $2,000,000 $2,000,000 0% $2,000,000 Feb-16 Feb-16 Jun-14 Jun-19
Light Rail Program
New Rail Corridors Study Planning $1,300,000 $2,981,955 129% $2,986,181 Feb-05 Dec-05 Feb-07 Jun-19
LRT Extension to Vasona Junction Planning $106,076,000 $176,000,000 66% $20,924,220 increase icon Jun-07 Jun-09 Jun-12 Mar-36
CELR - Eastridge Transit Center Construction $51,046,000 $59,225,031 16% $71,431,839 increase icon Jun-09 Oct-10 Jun-14 Dec-19
Northern Light Rail Express Close-out $34,850,000 $58,824,393 69% $66,135,106 increase icon Feb-11 May-12 Dec-18 Aug-17
CELR - Ph.II - LRT to Eastridge Planning $390,558,856 $376,900,000 -3% $70,000,157 decrease icon Jun-12 Jun-06 Jun-18 Dec-25
Santa Clara Pocket Track Close-out $10,000,000 $30,815,904 208% $30,815,904 increase icon Jun-13 Jun-13 Jun-15 Dec-19
N.1st Speed Improve. & 1st/Tasman Mods Design $7,000,000 $7,000,007 0% $7,000,007 Dec-16 Jul-15 Dec-17 Jun-19
Winchester LR Line Dbl Trk & Pltform Ext Planning $2,000,000 $22,000,042 1000% $22,000,062 Dec-16 Jun-16 Dec-17 Jun-25
SR 85 Major Transit Investment Study Planning $2,600,000 $600,027 -77% $600,027 increase icon Sep-16 Oct-16 Dec-19 Dec-19
Commuter Rail Program
SC Sta. Pedestrian Underpass Extension Construction $7,000,000 $13,080,997 87% $13,759,030 increase icon Mar-07 Jun-08 Jul-09 Dec-17
Caltrain Electrification Engineer Review Planning $2,800,000 $1,311,609 -53% $1,311,609 Jun-09 Jun-09 Jun-13 Dec-36
Caltrain Electrification Invest. Program Ongoing $60,000,000 $60,293,719 0% $60,293,719 Jun-13 Dec-12 Jun-22 Jun-20
Caltrain Safety Enhancements Design $8,000,000 $15,789,728 97% $31,415,163 increase icon Feb-07 May-07 Jun-12 Dec-21
Bus Program
Alum Rock/Santa Clara BRT Project Construction $127,600,000 $148,098,318 16% $148,098,318 decrease icon Jun-09 Dec-08 Jun-12 Dec-17
Stevens Creek BRT Project Planning $188,860,724 $4,382,516 -98% $4,382,516 decrease icon Apr-11 Jun-09 Oct-12 Dec-19
El Camino Real BRT Planning $216,000,000 $24,102,132 -89% $24,102,132 Dec-11 Jun-09 Jan-14 Jun-18
Procurement of BRT Articulated Buses Procurement $48,000,000 $57,654,131 20% $57,654,131 Dec-11 Jun-09 Jan-16 Jun-18
King Road BART BRT Planning $1,051,000 $8,023,759 663% $3,023,764 decrease icon Sep-11 Jun-11 Oct-12 Dec-21
Mod.of Chaboya & North Div.for BRT Buses Planning $12,830,950 $14,425,096 12% $14,427,488 increase icon Jun-12 Jun-12 Mar-14 Dec-19
BART Transit Integration Analysis Planning $2,000,000 $841,715 -58% $841,715 increase icon Jun-13 Jun-13 Jun-15 Dec-19
De Anza College Transit Ctr Improvements Planning $10,000,000 $7,734,295 -23% $7,734,354 Nov-15 Jun-15 Oct-16 Jun-21
Rapid 523 Bus Stop Improvements Construction $3,900,000 $3,900,749 0% $3,900,749 Apr-16 Apr-16 Jun-18 Jun-18
Stelling Road Bus Stop Improvement Proje Construction $1,600,000 $1,879,389 17% $1,600,169 Jan-17 Dec-16 Dec-17 Jun-18
Airport People Mover
San Jose Mineta APM Planning $800,000,000 $5,026,094 -99% $5,026,094 Jun-07 Apr-08 Dec-19 Dec-36
Project Locations (VTP Highway)
* Projects classified as Systemwide are not reflected on the map.

To see a project name, zoom in and hover over a locator on the map above. For details on the project click the link.

Projects By Phase (VTP Highway)
Current Appropriation by Project Type (VTP Highway)

Project Details (VTP Highway) Data Download Report Glossary
Budget Schedule
Project Name Photos Phase Original Cost Estimate Current Cost Estimate Original Estimate vs. Current Current Appropriation Scope Change Original Start Current Start Original Completion Current Completion
Highway
I-880/I-280 Improvements(Stevens Creek) Close-out $110,000,000 $65,988,016 -40% $66,015,842 decrease icon Jun-07 Dec-02 Dec-14 Sep-17
SR 87 Corridor Study Planning $225,000 $225,000 0% $225,000 Apr-17 Apr-17 Apr-18 Mar-18
SR 152 Realignment Planning $450,000,000 $31,390,189 -93% $31,390,189 Jun-09 Apr-07 Jun-13 Dec-19
Rt 87/Narvaez Interchange Planning $800,000 $800,000 0% $800,000 Jun-07 Dec-11 Jun-08 Dec-22
Ramp Metering Implementation Construction $3,500,000 $11,787,500 237% $11,787,500 Jun-07 Aug-08 Jun-08 Dec-17
Rt 237/Rt 101 Mathilda Interchange Planning $25,000,000 $35,846,757 43% $35,846,757 Jun-08 May-09 Jun-16 Jan-20
US 101/Capitol Expwy/Yerba Buena Interch Close-out $40,000,000 $30,523,050 -24% $33,190,208 Mar-10 Apr-10 Dec-11 Oct-17
Freeway Performance Initiative–Design Ph Construction $7,562,500 $7,000,000 -7% $7,000,000 Jan-11 Aug-11 Jun-15 Mar-19
SR 237 Express Lanes-Phase II Extension Design $20,000,000 $20,978,479 5% $20,978,479 Dec-11 Mar-12 Dec-15 Mar-20
I-280/Foothill Expressway Ramp Improv. Design $2,700,000 $4,054,020 50% $3,200,000 Jun-12 Mar-12 Jun-14 Dec-20
Combined Landscaping & Maint. Project Construction $3,722,000 $3,824,254 3% $3,824,254 Oct-12 Oct-12 Nov-16 Dec-20
101 Express Lanes - 101 San Mateo Planning $4,000,000 $2,000,000 -50% $2,000,000 Jun-13 Nov-16 Dec-19 Jun-18
Charcot Avenue Extension over I-880 Planning $4,500,000 $100,000 -98% $100,000 Jun-13 Jun-13 Dec-16 Dec-17
Innovat. Transportation Technology Prog. Planning $7,000,000 $2,000,000 -71% $2,000,000 Jun-13 Jun-15 Dec-16 Jun-18
Intelligent Transportation System Proj. Planning $16,000,000 $14,000,000 -12% $14,000,000 Jun-14 Jun-14 Dec-16 Mar-18
Landscaping@ I-280/I-880/StevensCrk Blvd Design $3,500,000 $3,339,235 -5% $3,500,000 Jun-13 Jun-13 Dec-16 Dec-22
US 101 / Buena Vista Avenue Planning $4,650,000 $4,000,000 -14% $4,000,000 Jun-14 Jun-17 Jun-16 Dec-21
US 101 SB Ramp Improv.10th St. in Gilroy Planning $3,600,000 $3,600,000 0% $3,600,000 Jun-13 Jun-18 Dec-16 Jun-22
Silicon Valley Express Lanes - I-880 Planning $35,000,000 $4,000,000 -89% $4,000,000 Jun-13 Jun-18 Dec-16 Jun-23
101 SB SanAntonio/Charleston/Rengstorff Planning $4,000,000 $4,000,000 0% $4,000,000 Dec-14 Jun-18 Dec-16 Oct-25
US 101/Old Oakland Road Improvements Planning $3,450,000 $3,450,000 0% $3,450,000 Jun-13 Jun-18 Dec-16 Dec-25
Capitol Expy-Ped Connection to Eastridge Procurement $1,547,400 $1,547,400 0% $1,547,400 Sep-14 Sep-14 Oct-18 Dec-19
SV Express Lanes-US101/SR85 PH 3 Design $35,800,000 $36,300,000 1% $36,300,000 Nov-14 Dec-15 Jun-19 Jun-22
SV Express Lanes-US101/SR85 PH 4 Design $11,400,000 $11,400,000 0% $11,400,000 Nov-14 Dec-15 Jun-19 Jun-22
SV Exp.Lanes-Electronic Toll System(ETS) Planning $47,221,000 $14,868,680 -69% $14,868,680 Dec-15 Feb-15 Jun-24 Jun-24
Noise Reduction Program on SR85 Planning $7,375,000 $2,375,000 -68% $2,375,000 Nov-14 Dec-15 Aug-19 Dec-20
I-280 Winchester Study Planning $671,000 $3,500,000 422% $3,500,000 Nov-14 Aug-16 Jun-17 Dec-23
I-280 Corridor Study Planning $750,000 $750,000 0% $750,000 Nov-14 Jan-15 Mar-16 Aug-17
Bicycle Safety Educat./Promotional Act. Planning $142,512 $142,512 0% $142,512 May-15 May-15 Jun-16 Mar-19
Local PDA Planning- Santa Clara Procurement $1,015,475 $1,015,475 0% $1,015,475 Jul-15 Jul-15 Dec-17 Dec-17
Story-Keyes Complete Sreet CorridorStudy Planning $451,824 $451,824 0% $451,824 May-15 May-15 May-17 May-18
Freeway Performance Initiative Ph 2 Planning $2,000,000 $2,000,000 0% $2,000,000 Jun-15 Jun-16 Jun-16 Jun-18
SV Express Lanes-Future Phase Project A Planning $135,000,000 $15,000,000 -89% $15,000,000 Dec-16 Jun-18 Jun-23 Jun-23
SV Express Lanes-Future Phase Project B Planning $135,000,000 $15,000,000 -89% $15,000,000 Dec-16 Jun-18 Jun-23 Jun-23
US101/Zanker Rd/Skyport Dr/N 4th St Inte Planning $125,000,000 $8,000,000 -94% $8,000,000 Jun-15 May-16 Aug-21 Dec-23
SR 237 Improv - Lawrence Expway to US101 Planning $22,000,000 $2,000,000 -91% $2,000,000 Jun-15 Jun-18 Jun-22 Jun-22
I-280 Corridor Improv-Initiation Doc.Dev Planning $2,500,000 $2,500,000 0% $2,500,000 Nov-15 Feb-17 Jun-17 Aug-18
I-680 Corridor Improv-Initiation Doc.Dev Planning $2,500,000 $2,500,000 0% $2,500,000 Nov-15 Jun-17 Jun-17 Jun-19
I-680 Sound Walls Planning $4,459,000 $1,100,000 -75% $1,100,000 Jun-15 Jun-15 Jul-17 Aug-20
New Corridor Studies-SR87&237/I-880/SR17 Planning $2,000,000 $1,899,800 -5% $1,674,800 Jun-15 Apr-17 Jun-17 Jun-18
Countywide Bicycle Plan Update Planning $700,000 $700,000 0% $700,000 Jun-15 Jun-15 Dec-16 Jun-18
Countywide Traffic Signal Coord. Study Planning $170,000 $170,000 0% $170,000 Sep-15 Jul-18 Jun-17 Mar-20
Tasman Corridor Complete Streets Study Planning $1,927,300 $1,128,000 -41% $1,128,000 Jan-16 Jan-16 Dec-19 Dec-19
Bascom Corridor Complete Streets Study Planning $1,661,700 $1,119,000 -33% $1,119,000 Jan-16 Jan-16 Dec-19 Dec-19
I-280/Wolfe Rd Interchange Improv Proj Planning $64,400,000 $4,400,000 -93% $4,400,000 Dec-16 Jun-16 Dec-22 Sep-23
US101 Dela Cruz Blvd/Trimble Rd IC Impro Planning $800,000 $48,956,000 6020% $4,953,600 Dec-05 May-06 Dec-06 Dec-21