Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTA Transit
Project #: P-0572
Project Name: Bus Signal Priority
Category: Operating Facilities & Equipment
Project Location:
Systemwide
Project Scope and Status
Scope: Develop a corridor specific project plan for implementation of bus signal priority (BSP) in high volume transit corridors anywhere in VTA's service area.
Status: On-going implementation of Bus Signal Priority (BSP).
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-2%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Jun-07 Dec-16 80%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0572
Project Name: Bus Signal Priority
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Apr-06 Initial Budget Setup $911 $911