Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTA Transit
Project #: P-0675
Project Name: Pavement Management Program-FY09
Category: Operating Facilities & Equipment
Project Location:
Systemwide
Project Scope and Status
Scope: This project is part of a continuing program that provides pavement maintenance and repair to all VTA operational and administrative facilities. The remaining scope includes pavement repair at the North Yard.
Status: Initial surveys and evaluations for the North Division asphalt rehabilitation and striping was completed. Final design work began in July 2014 and is expected to complete in fall 2017 for construction contract advertisement.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Apr-12 Mar-18 Sep-18 92%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0675
Project Name: Pavement Management Program-FY09
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-08 Initial Budget Setup $717 $717