Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTA Transit
Project #: P-0762
Project Name: Guada Signal Assessment/SCADA Sys Replac
Category: Light Rail Way, Power & Signal
Project Location:
Systemwide
Project Scope and Status
Scope: This project will provide an assessment of the state of repair and condition of the overall VTA Light Rail Signal System and its ability to accommodate future planned light rail operating scenarios. Initial engineering is also included.
Status: Preliminary designs are in progress and field work is anticipated to begin in late 2016.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-82%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Jun-15 Nov-16 Aug-17 19%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0762
Project Name: Guada Signal Assessment/SCADA Sys Replac
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jul-11 Initial Budget Setup $3,500 $3,500