Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTA Transit
Project #: P-0771
Project Name: Update Santa Teresa Interlock Sig. House
Category: Light Rail Way, Power & Signal
Project Location:
See Map
Project Scope and Status
Scope: The scope of this project includes the rehabilitation and updating of the Santa Teresa Interlock System from the current relay system to an advanced Vital Logic Controller (VHLC) system with associated advanced monitoring and diagnostics.
Status: The construction contract was re-advertised and awarded by the VTA Board Award in January 2014. Field work began in summer 2014 and completed in early 2016. Follow up signal work will be completed by a new contract beginning in fall 2017.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
151%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Dec-13 Jan-14 May-18 84%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0771
Project Name: Update Santa Teresa Interlock Sig. House
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jul-11 Initial Budget Setup $860 $860
Feb-14 Transfer from other VTA Transit Program project Transfer In/Out $1,300 $2,160