Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTA Transit
Project #: P-0776
Project Name: LRV Body Shop-Dust Separation Wall
Category: Operating Facilities & Equipment
Project Location:
See Map
Project Scope and Status
Scope: This project will provide for the construction of a 6,120 sq. ft. (225ft x 24ft) dust separation wall at the Guadalupe Operations Division light rail vehicle maintenance body shop.
Status: Phase I design basis report completed in mid 2014 and Phase II design work completed in spring 2016. VTA Board awarded the construction contract in September 2016; field work has begun in winter 2016 and expected to complete in summer 2017.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
92%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Dec-13 Sep-16 Aug-17 73%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0776
Project Name: LRV Body Shop-Dust Separation Wall
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jul-11 Initial Budget Setup $545 $545
Jun-15 Biennial Budget Adoption Augment $500 $1,045