Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTA Transit
Project #: P-0819
Project Name: Ped Swing Gates Replacement
Category: Passenger Facilities
Project Location:
Systemwide
Project Scope and Status
Scope: This project will replace 110 existing spring-hinge pedestrian swing gates at various locations along VTA's light rail system. The existing swing gates will be replaced with new and improved gravity-hinge gates that are safer and more reliable.
Status: The first construction contract completed by August 2014 and the contract was closed out. The design for the second construction contract for various pedestrian swing gate replacements is forecast to begin in mid 2017 after grant funding is available.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
1211%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Oct-12 Dec-13 Mar-18 10%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0819
Project Name: Ped Swing Gates Replacement
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jul-12 Initial Budget Setup $370 $370
Jun-13 Transfer from other VTA Transit Program project Transfer In/Out $200 $570
Jun-15 Biennial Budget Adoption Augment $880 $1,450