Skip to Main Content Skip to Side Navigation Skip to Top Navigation
Home>Transparency>Open Data>Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTA Transit
Project #: P-0835
Project Name: Bus Stop Pavement/Duckout Improv. FY14
Category: Passenger Facilities
Project Location:
Systemwide
Project Scope and Status
Scope: The project is a part of the annual program that will identify, repair and make physical improvements at bus stops to ensure Americans with Disabilities Act (ADA) compliance and improve the overall passenger environment throughout Santa Clara County.
Status: Construction for FY14 bus stop improvements has completed in May 2016 and contract closeout is underway. FY16 bus stop construction contract was advertised in April 2017 and bid opening occurred in May; contract is anticipated to be awarded in June 2017.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-2%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Oct-14 Dec-15 Oct-17 57%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0835
Project Name: Bus Stop Pavement/Duckout Improv. FY14
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-13 Initial Budget Setup $1,044 $1,044
Sep-16 Transfer from other VTA Transit Program project Transfer In/Out $92 $1,136
Sep-16 Transfer to other VTA Transit Program project Transfer In/Out -$116 $1,020
Jun-17 Transfer from other VTA Transit Program project Transfer In/Out $112 $1,132