Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTA Transit
Project #: P-0836
Project Name: Infrastructure-Add'l ClipperFare Devices
Category: Passenger Facilities
Project Location:
Systemwide
Project Scope and Status
Scope: Design, construction, power and network connectivity, and infrastructure of additional Clipper Interface Devices (CID's), a fare validator, on the light rail platforms.
Status: Clipper card readers (CID's) installed on all platforms.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Mar-15 Jun-15 Nov-16 81%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0836
Project Name: Infrastructure-Add'l ClipperFare Devices
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-13 Initial Budget Setup $550 $550
Jul-16 Transfer to other VTA Transit Program project Transfer In/Out -$85 $465
Oct-16 Transfer from other VTA Transit Program project Transfer In/Out $60 $525
Oct-16 Transfer to other VTA Transit Program project Transfer In/Out -$50 $475