Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTA Transit
Project #: P-0843
Project Name: Upgrade Ohlone/Chynoweth Interlocking
Category: Light Rail Way, Power & Signal
Project Location:
See Map
Project Scope and Status
Scope: Redesign the existing relay based interlocking to incorporate an electronic vital processor based system keeping original operational functionality, using as much existing wayside infrastructure such as signal poles, loops, track circuits, signal heads.
Status: Preliminary evaluations are underway.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Apr-17 May-18 Mar-19 0%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0843
Project Name: Upgrade Ohlone/Chynoweth Interlocking
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-13 Initial Budget Setup $1,200 $1,200