Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTA Transit
Project #: P-0844
Project Name: Cerone Propane Tank Replacement
Category: Operating Facilities & Equipment
Project Location:
See Map
Project Scope and Status
Scope: Decommission, remove and dispose of one 30,000 gallon LPG tank installed in 1978 which has reached the end of its life cycle and install one replacement 10,000 gallon LPG tank.
Status: Preliminary reviews and stakeholder coordination are in progress. A task order will be issued in mid 2017 for the design service. Design documents will define workaround and construction phasing to mitigate impact to Operations.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
217%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Jun-17 Jun-18 Mar-19 5%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0844
Project Name: Cerone Propane Tank Replacement
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-13 Initial Budget Setup $350 $350
Mar-17 Transfer from other VTA Transit Program project Transfer In/Out $760 $1,110