Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTA Transit
Project #: P-0845
Project Name: Track Intrusion Abatement FY14
Category: Light Rail Way, Power & Signal
Project Location:
Systemwide
Project Scope and Status
Scope: The project will prevent track intrusions into light rail trackway at intersections and locations subject to trespassing. Improvements to include fencing, barriers, signage, flashing signs & pavement markings at approved locations by VTA Safety Committee
Status: Final design is underway and anticipated to complete in fall 2017 for construction contract advertisement.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Sep-16 Dec-17 Jul-18 11%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0845
Project Name: Track Intrusion Abatement FY14
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-13 Initial Budget Setup $2,000 $2,000