Skip to Main Content Skip to Side Navigation Skip to Top Navigation
Home>Transparency>Open Data>Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTA Transit
Project #: P-0847
Project Name: Paving Management Program FY14
Category: Operating Facilities & Equipment
Project Location:
Systemwide
Project Scope and Status
Scope: Seal-coat work/paving of 30 parking lots and other VTA paving assets.
Status: Work is on a lower priority due to other projects that have been parked for a number of budget cycles, work is anticipated to begin in FY 15.This project is being reassigned to K. Ronsse in ETID.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Feb-15 Jul-15 Oct-16 36%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0847
Project Name: Paving Management Program FY14
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-13 Initial Budget Setup $2,316 $2,316