Project Scope, Status, Cost and Budget
Project Scope, Status, Cost and Budget
As of 6/30/2017Program: | VTA Transit |
Project #: | P-0850 |
Project Name: | SAP Plant Maint. & Materials Management |
Category: | Information Sys & Technology |
Project Location: |
|
Project Scope and Status
Scope: Purchase and install Synactive GuiXT console optimization and mobile solution packages for SAP Plant Maintenance and Materials Management. |
Status: Waiting for full Light Rail Component tracking implementation before proceeding with project kick-off |
Project Cost and Budget
Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%
0%
|
|
No Indicator: Percentage is within +10% and -10% tolerance. |
Project Milestones
Milestone Glossary
Design Start |
Construction/ Procurement Start |
Construction/ Procurement Complete |
Percent Complete |
---|---|---|---|
Feb-15 | Jun-15 | Jul-16 | 0% |
Budget History ($ in thousands)
Budget History Glossary
Program: | VTA Transit |
Project #: | P-0850 |
Project Name: | SAP Plant Maint. & Materials Management |
Date | Budget Change Description | Change Type | Amount |
Cumulative Total Appropriation |
---|---|---|---|---|
Jun-13 | Initial Budget Setup | $300 | $300 |