Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTA Transit
Project #: P-0905
Project Name: Multimodal TripDataCollector/Planner APP
Category: Information Sys & Technology
Project Location:
Systemwide
Project Scope and Status
Scope: Use open source software, API's and agency data to complete the build out of the conceptualized multimodal open trip planner from a previous proof of concept.
Status: Updating trip planner infrastructure and improving net user interface for the web based version.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
120%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
79%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0905
Project Name: Multimodal TripDataCollector/Planner APP
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Dec-14 Initial Budget Setup $125 $125
Jun-15 Transfer from other VTA Transit Program project Transfer In/Out $150 $275