Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTA Transit
Project #: P-0922
Project Name: SCADA Rehabilitation
Category: Light Rail Way, Power & Signal
Project Location:
Systemwide
Project Scope and Status
Scope: Phase 1 involves safety certification, preliminary hazard analysis & minor SCADA rehabilitation required to be in compliance with CPUC. Phase 2 of this project will include additional SCADA rehabilitation to make the system stable.
Status: Phase 1 involving safety certification, preliminary hazard analysis, developing design criteria and engineering analysis completed and field work has begun and expected to complete in 2016. This is the work required to be in compliance with regulations.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-12%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Jun-15 Aug-15 Sep-16 71%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0922
Project Name: SCADA Rehabilitation
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $2,041 $2,041
Oct-16 Transfer to other VTA Transit Program project Transfer In/Out -$50 $1,991
Oct-16 Transfer to other VTA Transit Program project Transfer In/Out -$187 $1,803