Skip to Main Content Skip to Side Navigation Skip to Top Navigation
Home>Transparency>Open Data>Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTA Transit
Project #: P-0924
Project Name: 40' Bus Procurement FY16
Category: Revenue Vehicles & Equipment
Project Location:
Systemwide
Project Scope and Status
Scope: Replacement project of eighty (80) buses, combination of 40' and 35', that have reached the end of their designed economic life.
Status: Project approved July 2015. VTA staff will begin developing specifications once project is fully funded.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-6%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Nov-15 Jun-16 Apr-19 0%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0924
Project Name: 40' Bus Procurement FY16
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $60,875 $60,875