Project Name: Bridge and Structure Repairs FY16
Category: Light Rail Way, Power & Signal
Project Location:
Systemwide
Project Scope and Status
Scope: The inspection of VTA Light Rail Bridge and Structure has been completed in accordance with CPUC requirements. The findings indicate that a number of structures are showing defects that either need further detailed investigation or require corrective work
Status: Project will begin once funding becomes available.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-53%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Sep-17 Sep-18 May-19 0%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0938
Project Name: Bridge and Structure Repairs FY16
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $700 $700