Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTA Transit
Project #: P-0948
Project Name: Light Rail Station Signage Replacement
Category: Passenger Facilities
Project Location:
Systemwide
Project Scope and Status
Scope: Replace wayfinding signage at all light rail stations to coincide with new light rail operating plan. Update VTA logo on platform entry pylons.
Status: Input received from operations, branding, BART, and construction. Signage needs identified, and graphics have been completed. Final design is anticipated to complete in summer 2017 for construction contract advertisement.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Jun-16 Sep-17 Mar-18 16%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0948
Project Name: Light Rail Station Signage Replacement
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $2,000 $2,000