As of 6/30/2017
Program: VTA Transit
Project #: P-0954
Project Name: Vasona Corridor Pedestrian Back Gates
Category: Passenger Facilities
Project Location:
Systemwide
Project Scope and Status
Scope: This project will install automatic pedestrian gates, swing gates & railings at several Vasona crossings at the off-quadrants. Crossings include but not limited to: Sunol,Auzerais,Lincoln,Parkmoor/Race, Fruitdale,Leigh,Stokes,Bascom,Campbell,Orchard City.
Status: Work will begin when grant funding is available.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Sep-17 Oct-18 Dec-20 0%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0954
Project Name: Vasona Corridor Pedestrian Back Gates
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $1,300 $1,300