Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTA Transit
Project #: P-0962
Project Name: Chaboya Yard Well Removal
Category: Operating Facilities & Equipment
Project Location:
See Map
Project Scope and Status
Scope: This project is to obtain case closure and demolish the ground water remediation system and wells at the Chaboya Yard. Work includes the abandonment of 50 monitoring wells & 5 extraction wells, closure for 2 groundwater extraction & 1 recharge trenches.
Status: Work will begin when grant funding is available.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Sep-17 May-18 Oct-18 0%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0962
Project Name: Chaboya Yard Well Removal
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $245 $245