Project Scope and Status
Scope: Preparation of a Diridon Station Intermodal Conceptual Plan to accommodate future transportation needs while promoting the best use of the lands within the Diridon Station area.
Status: Development of alternatives and criteria underway.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
500%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
7%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0989
Project Name: Diridon Sta. Intermodal Conceptual Plan
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Dec-16 Initial Budget Setup $1,000 $1,000