Skip to Main Content Skip to Side Navigation Skip to Top Navigation
Home>Transparency>Open Data>Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTA Transit
Project #: P-0999
Project Name: Paratransit Fleet Program
Category: Revenue Vehicles & Equipment
Project Location:
Systemwide
Project Scope and Status
Scope: Procure 30 Class A El Dorado National Aerolite 210 cutaway vehicles and associated equipment for paratransit services.
Status: Vehicles arrived and were paid for. Waiting for graphics to be installed.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Nov-16 Aug-17 0%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0999
Project Name: Paratransit Fleet Program
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Sep-16 Initial Budget Setup $2,323 $2,323