Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTP Highway
Project #: P-0565
Project Name: US101 Dela Cruz Blvd/Trimble Rd IC Impro
Category: Highway
Project Location:
See Map
Project Scope and Status
Scope: The project will study improvements to the US 101 - De La Cruz Boulevard/Trimble Road interchange.
Status: Project approval and environmental documentation (California Environmental Quality Act (CEQA)) phase was approved in early March 2016.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
6020%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Apr-18 Oct-18 Oct-20 2%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-0565
Project Name: US101 Dela Cruz Blvd/Trimble Rd IC Impro
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Dec-05 Initial Budget Setup $100 $100
Jun-07 Biennial Budget Adoption Augment $600 $700
Jun-08 Biennial Budget Adoption Augment $100 $800
Jul-09 Biennial Budget Adoption Augment $2,050 $2,850
Jun-10 Biennial Budget Adoption Augment $2,050 $4,900
Mar-12 Transfer from other VTP Highway Program project Transfer In/Out $54 $4,954