Skip to Main Content Skip to Side Navigation Skip to Top Navigation
Home>Transparency>Open Data>Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTP Highway
Project #: P-0655
Project Name: Ramp Metering Implementation
Category: Highway
Project Location:
Systemwide
Project Scope and Status
Scope: Implement ramp metering on SB US 101 (SB from Embarcadero to De La Cruz Boulevard & from SR 85 South to ), SR 85 (Almaden Expwy to Cottle Rd & US 101 north to I-280), SR 87, I-280 (US 101 to Hwy 17), and I-680 (Scott Creek Rd to US 101).
Status: Completed implementation of ramp metering on NB SR87, SB SR87 & SB 85, SB US101, SB I-880, & I-280. Provide assistance to MTC to implement metering on SR85, I-680 & US 101 South County corridors.SR=State Route.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
237%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Nov-08 Jul-09 Sep-17 21%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-0655
Project Name: Ramp Metering Implementation
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Oct-07 Initial Budget Setup $3,500 $3,500
Jul-09 Biennial Budget Adoption Augment $5,000 $8,500
Jun-10 Biennial Budget Adoption Augment $5,000 $13,500
May-11 Transfer to other VTP Highway Program project Transfer In/Out -$1,712 $11,788