Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTP Highway
Project #: P-0812
Project Name: I-280/Foothill Expressway Ramp Improv.
Category: Highway
Project Location:
See Map
Project Scope and Status
Scope: Widening the existing northbound I-280 exit to Foothill Expressway from one lane to two lanes and construct 4ft shoulder with retaining wall and concrete barrier. The project area extends from SR 85 connector ramp to NB I-280 and to Foothill Expressway.
Status: Completed 100% Design and provided to Caltrans. Seeking funds for construction.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
50%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Jun-12 17%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-0812
Project Name: I-280/Foothill Expressway Ramp Improv.
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
May-12 Initial Budget Setup $700 $700
Jun-13 Biennial Budget Adoption Augment $2,000 $2,700
Jun-15 Biennial Budget Adoption Augment $500 $3,200