Program: VTP Highway
Project #: P-0863
Project Name: Charcot Avenue Extension over I-880
Category: Highway
Project Location:
See Map
Project Scope and Status
Scope: This project will construct a new east/west connection of Charcot Ave over I-880. It will extend the existing Charcot Ave approx 1/4 mile.
Status: Project was initially included in Biennial Budget as CSJ entered into coop agreement w/VTA for environmental phase. City is now undertaking this project. Project to remain open until it is determined that VTA support is not required for subsequent phases.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-98%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
0%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-0863
Project Name: Charcot Avenue Extension over I-880
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-13 Initial Budget Setup $4,500 $4,500
Nov-15 Transfer to other VTP Highway Program project Transfer In/Out -$4,400 $100