Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTP Highway
Project #: P-0864
Project Name: Innovat. Transportation Technology Prog.
Category: Highway
Project Location:
Systemwide
Project Scope and Status
Scope: To provide ITS/tech related imprvments through projects to involve advanced express lanes enforcement tech,demand responsive/adaptive ramp metering,remote ramp mtring ctrl system,credit-based congestion pricing, mobile/web apps to report graffiti/pothole.
Status: Final Report on Impact on Emerging Technologies on Silicon Valley Express Lanes completed in Spring 2017. Remaining new project tasks are TBD and pending funding.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-71%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
4%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-0864
Project Name: Innovat. Transportation Technology Prog.
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-13 Initial Budget Setup $2,000 $2,000