As of 6/30/2017Program: | VTP Highway |
Project #: | P-0865 |
Project Name: | Intelligent Transportation System Proj. |
Category: | Highway |
Project Location: |
|
Project Scope and Status
Scope: To implement technology-based improvements for transportation systems. Implementation to include all phases of project development (e.g., environmental clearance, design & construction). |
Status: Project started initial outreach to stakeholders to develop the goals and vision of the strategic ITS plan for the County. Future workshops will be held to further develop the plan. |
Project Cost and Budget
Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-12%
-12%
|
|
No Indicator: Percentage is within +10% and -10% tolerance. |
Project Milestones
Milestone Glossary
Design Start |
Construction/ Procurement Start |
Construction/ Procurement Complete |
Percent Complete |
---|---|---|---|
Oct-15 | Oct-15 | Dec-17 | 0% |
Budget History ($ in thousands)
Budget History Glossary
Program: | VTP Highway |
Project #: | P-0865 |
Project Name: | Intelligent Transportation System Proj. |
Date | Budget Change Description | Change Type | Amount |
Cumulative Total Appropriation |
---|---|---|---|---|
Jun-13 | Initial Budget Setup | $14,000 | $14,000 |