Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTP Highway
Project #: P-0866
Project Name: Landscaping@ I-280/I-880/StevensCrk Blvd
Category: Highway
Project Location:
See Map
Project Scope and Status
Scope: This project includes landscaping planting, irrigation systems and plant establishment of the I-280/I-880/Stevens Creek Blvd. Interchange.
Status: Cooperative agreement with Caltrans signed in May 2015. Design began in September 2015 and is complete; seeking federal funds for construction. Construction contract advertisement planned for summer 2017.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-5%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Aug-15 Jul-17 Dec-21 22%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-0866
Project Name: Landscaping@ I-280/I-880/StevensCrk Blvd
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-13 Initial Budget Setup $3,500 $3,500