Home>Transparency>Open Data>Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTP Highway
Project #: P-0898
Project Name: Capitol Expy-Ped Connection to Eastridge
Category: Highway
Project Location:
See Map
Project Scope and Status
Scope: Construction of pedestrian crossing, signal modifications and safety fence installation.
Status: Environmental clearance was completed in June 2015. Descoped due to funding shortfall. Redesign will be completed in Dec 2016; obtaining HSIP fund for construction and advertisement occurred in May 2017. Construction is expected to complete by early 2018.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Feb-15 Aug-17 Mar-18 35%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-0898
Project Name: Capitol Expy-Ped Connection to Eastridge
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Oct-14 Initial Budget Setup $1,547 $1,547