Home>Transparency>Open Data>Project Scope, Status, Cost and Budget
Project Scope, Status, Cost and Budget
Project Scope, Status, Cost and Budget
As of 6/30/2017Program: | VTP Highway |
Project #: | P-0972 |
Project Name: | US101/Zanker Rd/Skyport Dr/N 4th St Inte |
Category: | Highway |
Project Location: |
|
Project Scope and Status
Scope: This is Phase 1 of project to construct a new interchange at US 101 to connect Zanker Road & Old Bayshore Highway with North Fourth Street & Skyport Drive. Phase 1 will improve limited existing connectivity across US 101 to N. San Jose employment centers. |
Status: Project Initiation Document (PID) phase is in progress and scheduled for completion in Summer 2017. |
Project Cost and Budget
Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-94%
-94%
|
|
No Indicator: Percentage is within +10% and -10% tolerance. |
Project Milestones
Milestone Glossary
Design Start |
Construction/ Procurement Start |
Construction/ Procurement Complete |
Percent Complete |
---|---|---|---|
Feb-19 | Dec-21 | May-23 | 12% |
Budget History ($ in thousands)
Budget History Glossary
Program: | VTP Highway |
Project #: | P-0972 |
Project Name: | US101/Zanker Rd/Skyport Dr/N 4th St Inte |
Date | Budget Change Description | Change Type | Amount |
Cumulative Total Appropriation |
---|---|---|---|---|
Jun-15 | Initial Budget Setup | $8,000 | $8,000 |