Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: VTP Highway
Project #: P-0978
Project Name: Countywide Bicycle Plan Update
Category: Highway
Project Location:
Systemwide
Project Scope and Status
Scope: Update of VTA's 2008 Countywide Bicycle Plan, with an emphasis on serving disadvantaged communities.
Status: Public Outreach finished in July 2016. Completed Cross County Bicycle Corridor updates in Fall 2016. Prioritization criteria adopted by VTA Board in Nov 2016. Corridor prioritization with staff recommendations to be made in Summer 2017.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Jun-16 Oct-17 86%
Budget History ($ in thousands) Budget History Glossary
Program: VTP Highway
Project #: P-0978
Project Name: Countywide Bicycle Plan Update
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $700 $700