Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: 2000 Measure A
Project #: P-0715
Project Name: Stevens Creek BRT Project
Category: Bus Program
Project Location:
See Map
Project Scope and Status
Scope: Stevens Creek Blvd/West San Carlos corridor project includes additional planning work to implement Rapid 523 service.Tasks include improvements to transit passenger environment, De Anza College Transit Center, complete streets imprvment, and env clearance
Status: Construction of bus stop improvements for Rapid 523 is now covered in Project P-0998. The project scope for P-0715 is to install Transit Signal Priority on Rapid 523. Six intersection in CSJ near Valley Fair need to be activated.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-98%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
May-12 Nov-16 Dec-17 83%
Budget History ($ in thousands) Budget History Glossary
Program: 2000 Measure A
Project #: P-0715
Project Name: Stevens Creek BRT Project
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jul-09 Initial Budget Setup $1,000 $1,000
Jul-11 Biennial Budget Adoption Augment $5,000 $6,000
Jul-14 Transfer from other 2000 Measure A Program project Admin Allocation $8 $6,008
Oct-14 Transfer from other 2000 Measure A Program project Admin Allocation $11 $6,019
Jan-15 Transfer from other 2000 Measure A Program project Admin Allocation $1 $6,020
Apr-15 Transfer from other 2000 Measure A Program project Admin Allocation $1 $6,021
Jun-15 Biennial Budget Adoption Augment $1,581 $7,602
Jul-15 Transfer from other 2000 Measure A Program project Admin Allocation $1 $7,603
Oct-15 Transfer from other 2000 Measure A Program project Admin Allocation $2 $7,604
Jan-16 Transfer from other 2000 Measure A Program project Admin Allocation $2 $7,606
Apr-16 Transfer from other 2000 Measure A Program project Admin Allocation $3 $7,610
Jun-16 Transfer to other 2000 Measure A Program project Transfer In/Out -$3,231 $4,378
Jul-16 Transfer from other 2000 Measure A Program project Admin Allocation $3 $4,382
Apr-17 Transfer from other 2000 Measure A Program project Admin Allocation $1 $4,383