As of 6/30/2017
Program: 2000 Measure A
Project #: P-0966
Project Name: N.1st Speed Improve. & 1st/Tasman Mods
Category: Light Rail Program
Project Location:
See Map
Project Scope and Status
Scope: Project will construct improvements to increase Light Rail Transit (LRT) speeds along North First Street corridor to 45 miles per hour.
Status: Project is in Conceptual Engineering. Specifications for this project will be developed by staff in mid 2017.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Jun-16 Dec-17 Dec-19 0%
Budget History ($ in thousands) Budget History Glossary
Program: 2000 Measure A
Project #: P-0966
Project Name: N.1st Speed Improve. & 1st/Tasman Mods
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $7,000 $7,000