Skip to Main Content Skip to Side Navigation Skip to Top Navigation
Home>Transparency>Open Data>Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 6/30/2017
Program: 2000 Measure A
Project #: P-1008
Project Name: Stelling Road Bus Stop Improvement Proje
Category: Bus Program
Project Location:
See Map
Project Scope and Status
Scope: The Stelling Road bus stop improvement will serve as an immediate solution to speed up travel time and accommodate increased transportation needs in the De Anza College area that will effectively result from implementation of the Rapid 523 line.
Status: Final design completed and construction contract was advertised in April 2017. Bid opening occurred in May and has been awarded by VTA Board in June. Field work will begin in summer 2017 and planned to complete in November 2017.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
17%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Jul-16 Jun-17 Nov-17 12%
Budget History ($ in thousands) Budget History Glossary
Program: 2000 Measure A
Project #: P-1008
Project Name: Stelling Road Bus Stop Improvement Proje
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Dec-16 Initial Budget Setup $1,600 $1,600