Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTA Transit
Project #: P-0689
Project Name: Traction Power Substation Procurement
Category: Light Rail Way, Power & Signal
Project Location:
See Map
Project Scope and Status
Scope: This project is part of continuing program that will replace the 14 Traction Power Substations (TPSS) that were installed at the Guadalupe Corridor, which are now over 20 years old.
Status: Phase 1 new TPSS for Younger Yard and replacement of TPSS 3&4 completed in mid 2015. Phase 2 TPSS 1,5&14 replacement completed in early 2015. Phase 3 was awarded in Oct 2016 (Base:TPSS 2,6;Opt1:13,Opt2:6,8,12); submittals approved & fabrications underway.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
17%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Mar-11 Jan-13 Mar-19 80%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0689
Project Name: Traction Power Substation Procurement
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Dec-08 Initial Budget Setup $2,700 $2,700
Jul-09 Biennial Budget Adoption Augment $5,400 $8,100
Jul-11 Biennial Budget Adoption Augment $5,400 $13,500
Apr-13 Transfer from other VTA Transit Program project Transfer In/Out $856 $14,356
Jun-13 Biennial Budget Adoption Augment $5,700 $20,056
Mar-14 Transfer from other VTA Transit Program project Transfer In/Out $204 $20,260