Home>Transparency>Open Data>Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTA Transit
Project #: P-0761
Project Name: Bridge Repair/Hamilton Struct.Stabilizat
Category: Light Rail Way, Power & Signal
Project Location:
See Map
Project Scope and Status
Scope: Based on the inspection of VTA Light Rail Bridges and Structures, funding for corrective actions is provided in this project.
Status: VTA Board awarded the contract in April 2014. Due to access issues, field work started in fall 2014 and completed in January 2015 with contract closed out. Final design is underway for Hamilton structure repair work & expected to complete in spring 2018.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
88%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Mar-12 Apr-14 Mar-19 64%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0761
Project Name: Bridge Repair/Hamilton Struct.Stabilizat
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jul-11 Initial Budget Setup $1,700 $1,700
Jun-15 Biennial Budget Adoption Augment $700 $2,400
Mar-16 Transfer from other VTA Transit Program project Transfer In/Out $400 $2,800
Jun-17 Biennial Budget Adoption Augment $400 $3,200