Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTA Transit
Project #: P-0818
Project Name: High Volume Bus Stop Improvement
Category: Passenger Facilities
Project Location:
Systemwide
Project Scope and Status
Scope: Improve conditions, upgrade amenities & improve safety @ bus stops along bus routes using the yet-TBD Transit Waiting Environment Study. This Study will be a guide to determine which corridors to prioritize for bus stop improvements & level of improvemnts
Status: Consultant report has been completed and VTA has begun final design for improvements to high volume bus stops. Final design is expected to complete in spring 2018 for construction contract advertisement.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-31%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Aug-17 Jun-18 Oct-18 14%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0818
Project Name: High Volume Bus Stop Improvement
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jul-12 Initial Budget Setup $750 $750
Sep-12 Transfer from other VTA Transit Program project Transfer In/Out $150 $900
Jun-13 Biennial Budget Adoption Augment $1,000 $1,900