Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTA Transit
Project #: P-0896
Project Name: Mobile Network-Full Fleet Wi-Fi
Category: Information Sys & Technology
Project Location:
Systemwide
Project Scope and Status
Scope: Implementation of WiFi connectivity in the bus fleet and upgrading it in the light rail vehicles. This is accomplished by installing a Moovbox in each vehicle which creates a WiFi network in the vehicle so that passengers can connect to the internet.
Status: All materials received. Approximately 75% buses and light rail vehicles have had Moovboxes installed.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Sep-14 Sep-14 Jun-18 88%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0896
Project Name: Mobile Network-Full Fleet Wi-Fi
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jul-14 Initial Budget Setup $650 $650