Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTA Transit
Project #: P-0914
Project Name: Core Connectivity Study
Category: Miscellaneous
Project Location:
Systemwide
Project Scope and Status
Scope: Compile mobility toolkit to close service gaps & improve access @ key rail stations including ride sharing/demand response service/carpooling/shuttles. Toolkit strategies may be applied to new BART stations (Milpitas,Berryessa) and other potential markets
Status: Waiting for final invoices for project close-out.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Nov-16 Nov-17 100%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0914
Project Name: Core Connectivity Study
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Feb-15 Initial Budget Setup $320 $320