Project Name: Guadalupe Train Wash Replacement
Category: Operating Facilities & Equipment
Project Location:
See Map
Project Scope and Status
Scope: Upgrade existing trench drains and concrete slab, replace reverse osmosis rinse system, and replace wash equipment and current blowers. The existing building would be reused with minimal modifications.
Status: The project will be on hold until funding is available and the new scope of work can be determined and what additional costs may be incurred to meet California water regulations.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Mar-18 Jan-19 Jul-19 0%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0932
Project Name: Guadalupe Train Wash Replacement
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $1,810 $1,810