Skip to Main Content Skip to Side Navigation Skip to Top Navigation
Home>Transparency>Open Data>Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTA Transit
Project #: P-0933
Project Name: Wheelchair Ramp Replacement on 70 Buses
Category: Revenue Vehicles & Equipment
Project Location:
Systemwide
Project Scope and Status
Scope: Replace wheelchair ramps in a total of seventy (70) forty-foot standard buses due to problems encountered by mobility device users.
Status: 12/14/17 Notice of intent to award issued, (69) LU-18 adjustable wheelchair ramps, awaiting only final signatures from supplier. One bus already equipped with updated ramp as a trial.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Sep-15 Jan-18 Jun-18 0%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0933
Project Name: Wheelchair Ramp Replacement on 70 Buses
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $1,050 $1,050