Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTA Transit
Project #: P-0943
Project Name: GIS Program Development
Category: Information Sys & Technology
Project Location:
Systemwide
Project Scope and Status
Scope: Develop all aspects of VTA's geographic information systems (GIS) program, including but not limited to cartography, database development, and spatial analysis.
Status: Project is in beginning phases of developing GIS Program. We are developing database specifications, cartographic specifications, open data policy, real time data access, asset management & much more.A variety of projects may have variety of consultants.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Jun-15 Jun-16 Jun-16 80%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0943
Project Name: GIS Program Development
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $250 $250