Skip to Main Content Skip to Side Navigation Skip to Top Navigation
Home>Transparency>Open Data>Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTA Transit
Project #: P-0950
Project Name: Pavement Management Program FY16
Category: Operating Facilities & Equipment
Project Location:
Systemwide
Project Scope and Status
Scope: Scope of work includes two years of pavement maintenance contract and one construction project for rehabilitation of VTA owned parking lots. Rehabilitation is patch, seal, and restripe.
Status: Work has been completed under this project. Project may be closed.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Mar-16 Mar-17 Oct-17 100%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0950
Project Name: Pavement Management Program FY16
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $910 $910