Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTA Transit
Project #: P-0958
Project Name: Traction/Substation Power Monitoring Sys
Category: Light Rail Way, Power & Signal
Project Location:
Systemwide
Project Scope and Status
Scope: Install new an energy management software program, ION Enterprise 7.2 interface, on a new server for Energy Power Monitoring System (EPMS) upgrade in traction power substations.
Status: RFP is being prepared and should be ready by September for 10 substations.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Aug-15 Oct-15 Dec-16 5%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-0958
Project Name: Traction/Substation Power Monitoring Sys
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-15 Initial Budget Setup $235 $235