Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTA Transit
Project #: P-1023
Project Name: Rail Replacement and Rehabilitation FY18
Category: Light Rail Way, Power & Signal
Project Location:
Systemwide
Project Scope and Status
Scope: The scope includes further rehabilitation and replacement of various track components at various locations including special track work switches, heel blocks,timber ties and defective/worn-out rail, and the repair & replacement of the Younger half-grand
Status: Work will begin when grant funding is available.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Jun-18 Aug-19 Dec-21 0%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-1023
Project Name: Rail Replacement and Rehabilitation FY18
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-17 Initial Budget Setup $17,100 $17,100