Project Scope and Status
Scope: Scope of work includes two years of pavement maintenance contract and construction projects for rehabilitation of VTA owned parking lots. Rehabilitation is patch, seal, and restripe.
Status: Paving Maintenance work has begun. Parking Lot rehabilitation has started design. A portion of the work encompassing 8 or 9 Park and Ride lots shall commence in Summer of 2018. Remaining parking lot rehabilitation is still in design.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Oct-17 Jun-18 Jun-19 4%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-1031
Project Name: Paving Management Program FY18
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-17 Initial Budget Setup $1,800 $1,800