Skip to Main Content Skip to Side Navigation Skip to Top Navigation
Home>Transparency>Open Data>Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTA Transit
Project #: P-1037
Project Name: Upgrade Hwy Rail Grade Crossing Ctrl Equ
Category: Light Rail Way, Power & Signal
Project Location:
Systemwide
Project Scope and Status
Scope: This project will upgrade existing highway rail grade crossing equipment such as controllers, relays, surge panels that have become obsolete and are no longer supported by the Original Equipment Manufacturer (OEM)
Status: Project will begin once grant funding is available.
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
0%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
0%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-1037
Project Name: Upgrade Hwy Rail Grade Crossing Ctrl Equ
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-17 Initial Budget Setup $5,460 $5,460