Project Scope, Status, Cost and Budget

Project Scope, Status, Cost and Budget

As of 12/31/2017
Program: VTA Transit
Project #: P-1039
Project Name: 40' Bus Procurement FY18
Category: Revenue Vehicles & Equipment
Project Location:
Systemwide
Project Scope and Status
Scope: Project will replace standard transit 40' buses, up to a quantity of (138), in order to retire existing buses which are significantly beyond their design life.
Status: RFP released and proposals being reviewed prior to requesting BAFO's
Project Cost and Budget Budget Detail Glossary
Change in Cost Estimate--Original vs Current
-56%  
 A cost estimate increase exceeding +10%
 A cost estimate decrease exceeding -10%
No Indicator: Percentage is within +10% and -10% tolerance.

Project Milestones Milestone Glossary
Design Start Construction/
Procurement Start
Construction/
Procurement Complete
Percent Complete
Jun-17 Nov-18 Jul-20 0%
Budget History ($ in thousands) Budget History Glossary
Program: VTA Transit
Project #: P-1039
Project Name: 40' Bus Procurement FY18
Date Budget Change Description Change Type Amount Cumulative Total
Appropriation
Jun-17 Initial Budget Setup $55,000 $55,000